3. Treat

Learn how to treat risks in Dastra.

The treatment step is the response given to the identified and assessed risk. In the risk page, it is the Risk response section.

Choose an option in the Risk response type field:

  • Mitigation and controls: measures must be implemented to reduce the risk;

  • Acceptance: the organization accepts the raw risk as it stands, without reduction measures;

  • Avoidance: the risk prevents the activity in question from being carried out;

  • Transferance: the risk weighing on the organization is transferred to another organization, for example through insurance;

  • Take risks: the risk should be subject to reduction measures, but the organization agrees not to implement them.

Risk response section with the five response options and the response justification
The Risk response section

Explain your choice in Response justification, then click Validate response to move to the Monitoring step. This decision belongs to the risk owner: only the owner can validate the response.

Only the Mitigation and controls option relies on control points and on the remediation rate, which move the current risk. For the other options, Dastra does not calculate a remediation rate.