Risk scoring
Compute one risk step by step on the default 5×5 scale and on the CNIL 4×4 scale, then see how the score of a data breach is calculated.
This example scores a risk of Brightmoor Retail Group twice, on two scales, then scores a data breach. The two calculations differ: the score of a risk is a product, the score of a data breach is a sum.
The risk
Brightmoor identifies the risk "Loss of customer payment data" on the processing activity "Online order management". In the Risk assessment section, Emma Walsh, the data protection officer, chooses a Severity and a likelihood for the initial risk, then for the residual risk once the controls are in place. See Assess a risk for the screen.
The score of a risk is severity × likelihood. The maximum score of a scale is the product of its two highest levels. Dastra shows the score as "score / maximum" and, in some views, as a percentage of the maximum.
On the default 5×5 scale
The default scale, Default risk heatmap, has five levels for each axis.
1
Negligible
Remote
2
Low
Unlikely
3
Medium
Possible
4
High
Likely
5
Extreme
Extreme
Brightmoor assesses the initial risk as High severity (4) and Possible likelihood (3). Card payments are processed by an external provider, but the order database holds the last digits and the billing address. After the controls (encryption, access reviews), the residual likelihood falls to Remote (1).
Initial
4
3
4 × 3
12 / 25
48%
red
Residual
4
1
4 × 1
4 / 25
16%
green

The percentage is the score divided by the maximum (25), rounded. The colour of the cell comes from the matrix of the scale: with five levels, the row is the severity counted from the top and the column is the likelihood.
The current risk lies between the two. After each response to a control point, Dastra recalculates it with this formula: current risk = initial risk − (initial risk − residual risk) × remediation rate. With a remediation rate of 50%, the current risk is 12 − (12 − 4) × 0.5 = 8. See Effect on the current risk.
On the CNIL 4×4 scale
Brightmoor decides to use the four-level scale of the CNIL method for privacy impact assessments. In Workspace settings > Risk management, a scale is created with the Risk profile template 4 levels - Classic DPIA and enabled with Save and enable the profile (see Configure the risk scale).
1
Negligible
10,000 €
Remote
25%
2
Low
50,000 €
Unlikely
50%
3
Medium
100,000 €
Possible
75%
4
High
1,000,000 €
Likely
100%

The values are the defaults of the template. They are editable, like the labels.
The same assessment, High severity (4) and Possible likelihood (3), now gives:
Initial
4
3
4 × 3
12 / 16
75%
red
Residual
4
1
4 × 1
4 / 16
25%
orange
The score is identical, but the maximum is lower, so the same risk weighs more: 75% instead of 48%, and the residual risk is orange instead of green. This is why Dastra asks for a confirmation before enabling another scale when risks exist, and why you should choose the scale before entering your first risks (see the FAQ).
A data breach
The incident module does not use the risk scales. In the Risk assessment step of a data breach, answer No to Risk assessment done?, then choose two scores from 1 to 4:
Data subject identification probability: how easy it is to identify people from the data;
Impact on data subject: the consequences for them.
The labels of the four values are 1 - Negligible, 2 - Limited, 3 - Important and 4 - Maximum. The score of the breach is their sum, from 2 to 8, and it sets the Risk level:
2 and 3
Low risk
Notification to the supervisory authority and communication to persons are not necessary
4 and 5
Medium risk
You must notify the supervisory authority
6 to 8
High risk
Notification to the supervisory authority and communication to data subjects mandatory
Brightmoor discovers that a customer export was readable for a few hours in a misconfigured storage space. It contains names, email addresses and order histories.
Export of order numbers only
2
1
2 + 1
3
Low risk
Export of names without contact data
3
1
3 + 1
4
Medium risk
Export of the customer file
4
2
4 + 2
6
High risk
For the third case, a product would give 4 × 2 = 8, but Dastra adds the scores: 4 + 2 = 6. This is already a High risk, so the notification to the supervisory authority and the communication to the data subjects are mandatory. See Document a new data breach for the step and the 72-hour counter.